  1. Stop the current Business Rules Server.

    Add Text
 

Recommended checkpoints

The databases should contain the newly added tables, which are namely as follows:

  • UM_DOMAIN

  • UM_SYSTEM_USER

  • UM_SYSTEM_ROLE

  • UM_SYSTEM_USER_ROLE

Going into production

Recommended tests

The following are the recommended tests to run on the staging system: 

  • Create multiple user stores and try adding users to different user stores.
  • Create multiple tenants and add different user stores to the different tenants. Thereafter, add users to the various user stores.
  • The staging database should be used as the new production database with the new Carbon server. The staging server should have the configurations equivalent to the production server. Map the production domain to the staging environment, once the staging environment is running smoothly. This migration should be done during a period when there is low traffic on the system.